  • Decision details

    Regeneration Partnership (Capital & Centric) Gateway 1 Report

    • Find out more about this issue
    • Printed decision PDF 58 KB

    Decision Maker: Cabinet

    Decision status: Recommendations Approved

    Is Key decision?: No

    Is subject to call in?: No

    Purpose:

    To provide Members with a summary of the Gateway 1 report produced by Capital and Centric (C&C), an assessment of the evidence base and the strength of the case for further work, and clear officer recommendations on why officers are not making a recommendation for the  Council to progress to Gateway 2. The Gateway 1 report is presented as received in final form from C&C save for necessary redactions; this overarching report does provide additional commentary and professional or technical opinion from Officers.

     

    The report also seeks to respond to the approved resolution by Overview and Scrutiny (Performance and Growth) of Councillor Martin’s motion from 4/11/26 against Cabinet Procedure rule 2.7. A copy of which is attached as Appendix 9, and also the request under Cabinet Procedure rule 2.8 for the item to be placed on the agenda

    Decision:

    The Cabinet has

     

    (1)  noted the receipt of the report at the end of Gateway 1, completion of Gateway 1 and the evidence base produced, including technical work and surveys, concept designs, pre-application advice, engagement data and the economic benefits assessment;

     

    (2)  noted that there is no formal decision required to cease work at the end of Gateway 1;

     

    (3)  noted that the Council does not intend to progress to Gateway 2 with Capital and Centric on the current schemes, for the reasons set out in the report; and

     

    (4)  noted that the independent review of the Capital and Centric commission and activity will continue as a separate process and that the technical evidence base will be retained and catalogued for potential future use.

    Reasons for the decision:

    As outlined within the report.

    Alternative options considered:

    As outlined within the report.

    Resource Implications:

    Gateway 1 expenditure has been set out elsewhere in this report.  No further expenditure on the current process is proposed. Closing the commission at the end of Gateway 1, will avoid any additional expenditure. Officer time will be required to manage the orderly close-down and to support the independent review. This is considered manageable within existing resources.

    Report author: Mike Gildersleeves, Pamela Scott

    Publication date: 24/11/2026

    Date of decision: 24/11/2026

    Decided at meeting: 24/11/2026 - Cabinet

    Accompanying Documents:

    • Regeneration Partnership (Capital & Centric) Gateway 1 report pdf icon PDF 387 KB
    • Appendix 1. Regeneration Opportunities - Huntingdonshire Market Towns - Redacted pdf icon PDF 9 MB
    • Appendix 2 - huntingdonshire locations & approach pdf icon PDF 69 MB
    • Appendix 3 - Huntingdonshire proposal development pdf icon PDF 151 MB
    • Appendix 4 - Huntingdonshire final design pack pdf icon PDF 43 MB
    • Appendix 5A - 240902 st ives presentation compressed pdf icon PDF 5 MB
    • Appendix 5B - 240923 st neots + huntingdon presentation pdf icon PDF 13 MB
    • Appendix 6A - huntingdon_consultation_analysis_capital_centric pdf icon PDF 123 KB
    • Appendix 6B - st_ives_consultation_analysis_capital_centric pdf icon PDF 160 KB
    • Appendix 6C - st_neots_consultation_analysis_capital_centric pdf icon PDF 159 KB
    • Appendix 7 - Pre App Comments pdf icon PDF 5 MB
    • Appendix 8 - Pre App responses pdf icon PDF 71 KB
    • Appendix 9 - GC InSight Economic Report pdf icon PDF 1 MB
    • Appendix 10 - Cllr R Martin Motion O&S (P&G) 04 11 26 pdf icon PDF 31 KB
    • Supplemental Document Cabinet 24th November 2026 pdf icon PDF 60 KB