82 HUNTINGDON TOWN CENTRE DEVELOPMENTS: REQUEST FOR RELEASE OF FUNDS PDF 16 KB
To consider a report by the Heads of Planning Services and of Financial Services regarding the funding of the Huntingdon Town Centre Medium Term Plan Scheme.
Contact: S Couper 388103
Decision:
Approved the release of funding for the Huntingdon Town Centre Development Scheme in 2005/06and in the event revenue savings fail to cover the impact of this change, approved a supplementary revenue estimate of up to £54,000 in the current year and the variations in revenue impact relating to 2005/06 onwards included in the medium term plan.
Minutes:
By way of a joint report by the Heads of Planning and of Financial Services (a copy of which is appended in the Minute Book) the Cabinet considered a request for the release of funding from the Medium Term Plan for a series of studies on issues likely to impact on the redevelopment and economic viability of Huntingdon Town Centre, some of which would involve a transfer from capital to revenue funding.
Whereupon, it was
RESOLVED
(a) that the release of funding for the Huntingdon Town Centre Development Scheme in 2005/06 be approved; and
(b) that, should revenue savings fail to cover the impact of the change referred to in (a) above, a supplementary revenue estimate of up to £54,000 in the current year be approved and the variations in revenue impact relating to 2005/06 onwards included in the Medium Term Plan.