90 HUNTINGDONSHIRE LOCAL PLAN TO 2036 QUARTERLY UPDATE PDF 241 KB
To receive a report by the Head of Development regarding an update on progress on preparation of the Huntingdonshire Local Plan to 2036.
Contact: C Bond 388435
Additional documents:
Decision:
That the Cabinet:
i. notes progress on preparation of the Huntingdonshire Local Plan to 2036 and its supporting evidence base; and
ii. agrees the establishment of a single Planning Policy earmarked reserve as set out in paragraph 4.1 of the submitted report.
Minutes:
The Cabinet considered a report by the Head of Development (a copy of which is appended in the Minute Book) to note the progress on preparation of the Huntingdonshire Local Plan to 2036 (HLP2036) and its supporting evidence base in the light of recent government announcements relating to the timescale for the production of local plans.
The government has announced that it expects new local plans ‘to be written’ by early 2017 although there has been no clarification of what statutory stage of preparation this referred to. The next stage of the preparation process for the HLP2036 would be the proposed submission stage, which was the first statutory stage. This involved a six week public consultation period, specifically inviting representations on issues of soundness and legal compliance.
When the Cabinet received an update in the previous quarter, the highest priority was the brief for a Strategic Transport Study. The Cabinet was informed that this had now been prepared and was being processed by Cambridgeshire County Council’s procurement team, with the intention that the contract was awarded in May 2016.
Revalidation work of the Cambridge Sub-Regional Model was currently being undertaken on behalf of Cambridgeshire County Council by Atkins. This work was necessary to ensure that the model incorporated the most up-to-date data on traffic demand, was updated with all recently completed transport infrastructure schemes and the public transport, walking and cycling assignments were correct. Due to the complexity and volume of data in the model the Cabinet was informed that the revalidation work would not be complete until the end of May/early June.
At the Cabinet meeting on 19th November 2015 it was resolved that ‘as a priority, infrastructure requirements for Wyton Airfield are further scoped with a view they can be identified and fully costed’. The Cabinet were referred to the four potential development scenarios that had subsequently been prepared to test.
Following appointment of JBA Consulting, work on the first element of the Strategic Flood Risk Assessment (SFRA) had commenced and was scheduled for receipt by the Council in late April 2016. This was later than originally scheduled due to delays in provision of extensive datasets by the Environment Agency. Completion of the second element of the SFRA was now anticipated in July 2016, subject to availability of Environment Agency inputs.
The Cabinet agreed that a county-wide approach to the replacement Gypsy and Traveller Needs Assessment (GTANA) being coordinated by the Joint Strategic Planning Unit on behalf of Huntingdonshire District Council, in partnership with a number of other Councils, was the best approach. The Cabinet also discussed the difficulties in allocating sites and was informed that a criteria based approach to guide site selection continued to be proposed. The Cabinet noted the difficulties that could be presented for schools when gypsy and travellers sites were granted at appeal. The Cabinet was informed that the GTANA would take account of the new, more restrictive definition of gypsy and traveller which had been published and was expected to result in ... view the full minutes text for item 90
27 LOCAL PLAN TO 2036 PROGRESS REPORT PDF 240 KB
The Local Plan To 2036 Progress Report is to be presented to the Panel.
Contact: A Moffat 388400
Minutes:
With the aid of a report by the Head of Development (a copy of which is appended in the Minute Book) the Local Plan To 2036 Progress Report was presented to the Panel. Members had been informed that the Environment Agency’s Strategic Flood Risk Assessment had progressed however the County Council’s Strategic Transport Study had not progressed.
In regards to the Strategic Transport Study the Panel was informed that the Cambridge Sub-Regional Model (CSRM) traffic model was flawed and requires revalidation which won’t be complete until the end of May and that in turn would put the submission of the Local Plan back to summer 2017.
Members noted that there will be an earmarked fund for the development of the Local Plan but were advised that the money is existing money.
Following a question on the County Council contribution towards the costs of developing the Local Plan Members were informed that the County Council would fund the work they would undertake but no additional funding would be offered.
When discussing the road infrastructure the Panel was informed that the Council would be looking beyond the A1 and A428. In regards to the A141 Members were advised that there is a requirement for the A141 to be upgraded regardless of whether Wyton gets developed or not.
Concerns were raised in relation to the human resources available to the department to carry out work on the Local Plan however the Panel were informed that there is a plan in place to acquire the resources needed.
Following a question on what is required by the Government by early 2017; Members were advised that the Council is still unsure what is meant by having a written Local Plan by early 2017.
Four potential development scenarios have been produced to be tested using the CSRM however the Panel will not make a preference until they have been tested.
The Panel are content with the overall progress on the Local Plan but were concerned that the CSRM was not correct. Members approved the earmarking of funds for the development of the Local Plan.