    Overview and Scrutiny Panel (Environment, Communities and Partnerships) - Thursday, 2 July 2026 7:00 pm

    • Attendance details
    • Agenda frontsheet PDF 118 KB
    • Agenda reports pack
    • Huntingdonshire's Community Health and Wealth Community Fund PDF 375 KB
    • Printed minutes PDF 64 KB

    Venue: LANCASTER & STIRLING, CIVIC SUITE, PATHFINDER HOUSE, ST MARY'S STREET, HUNTINGDON, PE29 3TN

    Contact: Mrs Beccy Buddle, Democratic Services Officer, Tel No: 01480 388008/e-mail  Beccy.Buddle@huntingdonshire.gov.uk 

    Media

    Items
    No. Item

    9.

    Minutes pdf icon PDF 65 KB

    To approve as a correct record the Minutes of the Overview and Scrutiny Panel (Environment, Communities and Partnerships) meeting held on 4th June 2026.

    Contact: B Buddle 01480 388008

    Minutes:

    The Minutes of the meeting of 4th June 2026 were approved as a correct record and were signed by the Chair.

    10.

    Members' Interests

    To receive from Members declarations as to disclosable pecuniary and other interests in relation to any Agenda item.

    Contact: B Buddle 01480 388008

    Minutes:

    No declarations were received.

    11.

    One Leisure Solar Installations Update pdf icon PDF 222 KB

    The Panel is to receive an update on the One Leisure Solar Panels Installations.

     

    Executive Councillor: Cllr D Mickelburgh

    Contact: M Raby (01480) 387921

    Additional documents:

    • 4. One Leisure Solar Installations Update Appendix A , item 11. pdf icon PDF 1 MB

    Minutes:

    By means of a report and presentation from the Head of Properties, Facilities and Health and Safety (copies of which are appended in the Minute Book), the update on the One Leisure Solar Installations was presented to the Panel.

     

    The Panel heard that the original specification had been based on 12 months of half hourly site data and optimising the install with sufficient to be able to run the site rather than excess. It was noted that if excess were generated the payback from the grid was approximately 30% of it’s worth. Whilst batteries were also considered they were not felt to offer value for money at the time of the installation. It was noted that the payback period of under 10 years was achievable with the installation, however had the panels been increased, this would have been extended into a longer payback period. It was further observed by officers that the project offered good value for money as the return on investment is maximised at each site along with the generation capacity. Data would be sought from other Councils to give some comparison on the efficiencies and cost effectiveness.

     

    It was clarified that the project at One Leisure St Ives had included a grant from Sports England towards the total cost of the project which allowed for additional improvements to be added to the project and an alternative with the carpark canopy panels. This meant a longer payback period however this was considered to be acceptable within the detail of the project.

     

    It was advised that due to emerging technologies the payback period of the One Leisure St Ives Outdoor site had changed since the initial plan, however this was still felt to represent good value for money and well within good practice, it also allowed for other opportunities to be explored such as utilising excess energy at other Council sites.

     

    It was agreed that an update on changes to energy contracts and the impact on costs would be sought and communicated back to the Panel. It was noted that the projected figures were very conservative and that it was anticipated this would shorten the projected payback periods as a result.

     

    It was observed that the previous expected payback period for solar panels had been 25 years so that the projected 7 years for the project was much improved. It was also encouraged that options for battery storage be developed in order to maximise efficiencies. It was noted that the One Leisure St Ives Outdoor site generated more electricity than it used during the day, therefore batteries had been investigated in order to store the generated energy to be utilised in the evening when energy would not be generated.

     

    The Panel heard that lessons had been taken away from the project and were useful in informing best practice and maximising opportunities for future projects. It was noted that the opportunity to install panels at Pathfinder House was currently underway along with identifying additional sites to maximise opportunities.

     

    It was  ...  view the full minutes text for item 11.

    12.

    Community Health and Wealth Strategy Update pdf icon PDF 234 KB

    To receive an update on the Community Health and Wealth Strategy.

     

    Executive Councillor: Cllr D Mickelburgh

     

    Report to follow

    Contact: C Deeth (01480) 388233

    Minutes:

    By means of a report and presentation from the Head of Communities and Operational Housing (copies of which are appended in the Minute Book), an update on the Community Health and Wealth Strategy was presented to the Panel.

     

    The Panel heard that where applications did not meet the criteria for funding, Officers liaised with applicants with wraparound support to either revise and finesse their application or signpost to alternative and more suitable funding opportunities. The Panel also heard that applications did not have to fill every box of the criteria but a scoring approach was undertaken to assess viability.

     

    It was advised that the team were mindful of the impending Local Government Reorganisation timelines and that clear guidelines were set with successful applicants relating to timescales for funding and achievability of projects within those timeframes. Work was also being undertaken to future proof the scheme so that it could continue longer term and that this would be monitored to ensure viability continued for as long as possible.

     

    It was noted that as part of the project and working alongside partners, work was undertaken to support young people into employment as well as supporting residents in crisis.

     

    The Officers undertook to supply further details to Councillors to empower them in supporting the scheme within their wards.

    13.

    Overview and Scrutiny Work Programme pdf icon PDF 85 KB

    a)  The Panel are to receive the Overview and Scrutiny Work Programme

    b)  Members to discuss future planning of items for the Work Programme

    c)  The Panel are to receive the Notice of Key Executive Decisions

     

    Contact: B Buddle 01480 388008

    Additional documents:

    • 3. Notice of Key Decisions , item 13. pdf icon PDF 143 KB

    Minutes:

    With the aid of a report by the Democratic Services Officer (a copy of which is appended in the Minute Book) an update on the Overview and Scrutiny Work Programme was presented to the Panel.

     

    An overview of the Panel’s requests for topics to be discussed was given alongside a rationale to show the consideration of these.

     

    An update was given on the agreed project to look at Community Safety Partnerships and Councillors Bulat, Burke, Bywater and Francis volunteered to be part of the Working Group over the summer, with a view to receiving an update report at the September meeting of the Panel.

     

    Councillor Alban expressed his view that updates on One Leisure and Hinchingbrooke Country Park activities should be sought with a view to them being planned into the October agenda. It was also noted that following a request on an update for the alternative fuels used by Operations, this would be brought to the October agenda.

     

    It was noted that two or three scrutiny topics per year was a sustainable number to sit alongside the pre-planned Council reports and scrutiny work.

     

    Councillor Alban reminded the Panel of the invite to the Great Fen project in September which had been arranged following requests from scrutiny.